Which term describes operations that involve the controlled use of a crane for work cycles?

Prepare for the EICA Mobile Crane and Digger Test with expert-crafted flashcards and multiple choice questions. With hints and detailed explanations, you're set to excel in your certification exam.

The term "duty cycle" refers to the operations that involve the controlled use of a crane for work cycles. This concept encompasses the various activities a crane performs during its operation, including lifting, moving, and placing loads. The duty cycle typically includes the duration of each lift, the frequency of lifts, and the overall workload the crane is expected to handle over a given period. Understanding the duty cycle is crucial for ensuring the crane operates safely and efficiently, allowing operators to plan their work accordingly, maximize productivity, and prevent overloading or wear on the equipment.

In contrast, continuous lifting refers to lifting operations that occur without interruption, which does not necessarily involve the controlled aspects of a cycle. Static load implies that the load is stationary while being supported by the crane, which doesn't capture the dynamic nature of crane operations. Dynamic lifting pertains to lifting operations involving movement or changes in load dynamics, which can complicate control but does not specifically address the structured approach denoted by duty cycle. Therefore, "duty cycle" is the most accurate term for controlled crane operations within defined work sequences.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy